When are the A40 Llanddewi Velfrey to Redstone Cross improvements due to be completed?
Answered by Cabinet Secretary for Transport and North Wales
| Answered on 19/03/2025
Section 1 of the A40 Llanddewi Velfrey to Redstone Cross Improvements Scheme is programmed for completion week commencing 28th April 2025, Section 2 i.e. the detrunking works through Llanddewi Velfrey village will commence thereafter.