WQ89351 (e) Tabled on 17/10/2023

Will the Minister outline the overall expected final cost of the Heads of the Valleys road scheme?

Answered by Deputy Minister for Climate Change | Answered on 27/10/2023

The below table sets out the expected final cost of the Heads of the Valleys road scheme.

A465

Expected final

Final Cost

Sec 1 Abergavenny to Gilwern

 

57m

Sec 2 Gilwern to Brynmawr

 

336.2m

Sec 3 Brynmawr to Tredegar

 

163.3m

Sec 4 Tredegar to Dowlais Top

 

57.8m

Sec 5&6 Dowlais Top to Hirwaun (since 2013 to 2025)

£122.5m capital until 2025 when the scheme is complete + Annual service payment of c£43m revenue for 30years from August 2024 when the first section of the scheme is open