WQ88920 (e) Tabled on 30/08/2023

Will the Minister provide an update on the Heads of the Valleys road project, including latest costs and estimated completion date?

Answered by Deputy Minister for Climate Change | Answered on 06/09/2023

The current Welsh Government costs to date for the A465 Sec 5 Dowlais Top to Hirwaun are £90.16m (since 2013 - July 2023) and the estimated completion date is Summer 2025.