WQ88605 (e) Tabled on 07/07/2023

Has the stand-alone model for the new Velindre Cancer Center with 31 beds been assessed as value for money, following construction costs increasing from £200 million in 2021 to £400 million in 2023?

Answered by Minister for Health and Social Services | Answered on 19/07/2023

The next Value for Money governance point is the Full Business Case which is due to be submitted to the Welsh Government in late Summer 2023.  As part of the detailed scrutiny that will be undertaken by Welsh Government Officials on the Full Business Case, Value for Money is a key element which will need to be demonstrated.