WQ83653 (e) Tabled on 20/10/2021

Will the Minister provide an update on the progress and cost of the Heads of the Valleys road project, including a date for completion?

Answered by Minister for Climate Change | Answered on 26/10/2021

The Heads of the Valleys dualling scheme was split into six sections to enable a phased delivery. Sections 1, 3 and 4 have been completed. Sections, 2 5 and 6 are currently under construction.

Section 4 Tredegar to Dowlais Top

  • Opened November, 2004
  • Cost £47m

Section 1 Abergavenny to Gilwern

  • Opened May, 2008
  • Cost £60m

Section 3 Brynmawr to Tredegar

  • Opened September 2015
  • Cost £158 million (Part-Funded by circa £78m of EU funding from the European Regional Development Fund).

Section 2 Gilwern to Brynmawr

  • Remains on target for completion this year.
  • Cost £336m

Sections 5 and 6 Dowlais Top to Hirwaun

  • End date: 2025
  • Cost £590m