WQ82463 (e) Tabled on 24/05/2021

Will the Minister provide an explanation as to why maintenance works is required on the Newtown bypass?

Answered by Deputy Minister for Climate Change | Answered on 02/06/2021

The company secured to build the Newtown bypass has a contractual obligation to maintain the landscaping and planting for 5 years after completion.  This may include verge grass cutting and maintenance or replacement of any planting that has not grown as expected, for example.  They also have a contractual obligation to rectify defects identified under the terms of their contract.

Following routine inspections, areas of planting have been identified where plants have died/not taken and these have been replaced.  In addition, areas of carriageway surface course have been identified as defective and these have also been replaced.