WAQ75248 (e) Tabled on 24/11/2017

Further to the written answer to WAQ74313, will the Cabinet Secretary confirm when the repairs to the railway bridge at Commins Coch on the A470 will commence?

Answered by Cabinet Secretary for Economy and Transport | Answered on 04/12/2017

The first of four weekend possessions was undertaken last weekend (25 November). Temporary works scaffold will be in place this weekend (2 December) and works to rebuild and repoint the structure will begin on 4 December. The contractor for the repairs to the safety barrier leading to and from the bridge will be on site on 29 November.