WAQ74331 (e) Tabled on 04/10/2017

Will the Cabinet Secretary provide an update on progress with regards the improvement works to junctions 15 and 16 on the A55, to include details of the public consultation, and a detailed timetable for development, consultation, design and construction?

Answered by Cabinet Secretary for Economy and Infrastructure | Answered on 10/10/2017

We recently appointed Carillion as the Early Contractor Involvement (ECI) contractor to progress the improvements of Junctions 15 and 16 on the A55. Over the next 18 months we will be progressing the design development of both junctions which will include public consultations. We are planning to hold Public Information Exhibitions towards the end of the year where further details of the programme for delivering the junction improvements will be presented.